AltaGas Ltd. Commissioning Activities for Forrest Kerr Hydro Facility on Schedule and on Budget

Forrest Kerr HydroOn 30-Jul-14, AltaGas Ltd. announced that it had started producing power at its 195 megawatt (MW) Forrest Kerr run-of-river hydroelectric facility.  Final commissioning of the powerhouse systems and high voltage switchyard were completed in July and the facility is now tied-in and delivering power to the Northwest Transmission Line at Bob Quinn, British Columbia.

In an article from Marketwired, 30-Jul-14, David Cornhill, Chairman and CEO of AltaGas was noted as saying the following: “We are pleased to announce that we have safely commissioned and energized the largest construction project in our history,” the article continues on, highlighting the CEO’s quote, “This significant milestone is truly remarkable and was made possible by the outstanding contributions of our dedicated employees and contractors, the Tahltan First Nation, BC Hydro and the Government of British Columbia.”

AltaGas Ltd. expects final project commercial operations to be achieved by the end of third quarter 2014.  The $725 million Forrest Kerr facility was completed on time and on budget. It is supported by a 60-year, fully indexed Electricity Purchase Agreement with BC Hydro.

AltaGas Ltd. is an energy infrastructure business with a focus on natural gas, power and regulated utilities. AltaGas creates value by acquiring, growing and optimizing its energy infrastructure, including a focus on clean energy sources.

For more information visit: www.altagas.ca and to view the original article  click here